Within Building #1, drywall installation and painting are progressing. The siding installation is in progress outside, while the MEPFP rough-in is finishing up inside.
Interior framing of the first floor of Building #2 and the exterior framing of the fourth floor is in progress. Additionally, we are preparing for window installation.
Building #3’s plumbing rough-in is moving along, and the roof installation has begun. The interior framing is wrapping up while the remaining windows are installed. Additionally, the siding installation has started.
The roof of the Club House (Building #4) is complete, MEPFP has begun, and the siding installation is in progress. The framing, roofing, and siding have also started for Garages #6 and #9.
Despite some unusual winter weather conditions, the Seacoast Residences team is doing an excellent job keeping this 270,000 GSF multi-family housing project on track. Great work, Team!