As the Bellows Free Academy wraps up its first few days back to school, we’re excited to share an update on the progress of the Renovations and Additions project in Fairfax, VT. Our team has worked diligently over the summer to make sure the school is fully prepared for students and staff.
Inside the building, we’ve made significant progress. We’ve removed the ceilings and the old fire alarm system to make way for the new sprinkler and fire protection system, including new water entrances. Extensive mechanical upgrades have been completed in the elementary wing. New ceilings and the sprinkler system have been installed in the elementary school corridors, administration offices, and classrooms. Additionally, we’ve relocated the data room in preparation for a new elevator installation planned for 2025, and we have completed the demolition and fit-up for the future science lab.
We’ve finished stormwater and sanitary improvements on the exterior with new structures and piping. We’ve begun work on a new heated ski wax space for students, including necessary HVAC upgrades. The main entrance has been excavated and is being prepared for a new canopy and decorative concrete planters. Concrete foundations for the three additions have been poured, setting the stage for steel erection in September. We’ve also updated sidewalks, drive lanes, and parking areas.
Looking ahead, we will continue working on the three additions and the library throughout the school year, targeting completion in late fall or early winter. To minimize disruption, work inside the school will be conducted during off-hours, weekends, and vacation periods.
These improvements will significantly upgrade the school’s infrastructure, creating a safer, more accessible, and modern learning environment. The project is expected to be completed by fall 2025 and will include 139,663 square feet of renovations and 17,922 square feet of new additions designed by Black River Design Architects.
A big thank you to everyone involved for their dedication and hard work. We’re excited to see the final result and the positive impact it will have on the Bellows Free Academy community.